NORTH MAIN STREET EMERGENCY PAVEMENT REPAIRS
PROJECT UPDATE – PAVING SCHEDULE
May 12, 2023
Be advised that emergency pavement repairs will be made to a section of North Main Street where a water main break recently occurred.
Pavement repairs will be conducted on the following days and times:
MONDAY, MAY 15th from 3:30 AM to NOON
Pavement milling and concrete base repair
THURSDAY, MAY 18th from 5 AM to NOON
Final paving of surface
During these days and times, North Main Street will be completely closed between Orange Street and River Street. Traffic will be detoured through River Street and West Street.
This work is being performed starting in the early hours of the day in order to minimize the overall impact to traffic flow in the village as well as the businesses in the affected area. We apologize for any inconvenience or noise disturbance.
Thank you for your patience and understanding as we work to complete this repair in an efficient manner.