2021 ROAD PROGRAM
Improvements to; Bell Street, Chagrin Blvd, West Summit Street, East Summit Street, West Orange Street, Longwood Drive, Edgewood Drive, Wilding Chase, Walnut Street and River Run Park parking lot
OVERVIEW
The annual Road Program is a yearly program that encompasses multiple projects with the aim to improve roadways throughout the Village.
TIME-FRAME
Start Date: October 18, 2021
Projected Completion Date: November 12, 2021
BUDGET
$547,083.00 [ Burton Scot Contractors ]
STATUS UPDATES
DATE | DESCRIPTION | RESOURCE(S) |
---|---|---|
10/06/2021 | Press Release: 2021 Road Program Starting | Document |
09/00/2021 | Bid Awarded to Burton Scot | |