PROJECT: 2021 Road Program

[ back to main construction projects page ]

2021 ROAD PROGRAM

Improvements to; Bell Street, Chagrin Blvd, West Summit Street, East Summit Street, West Orange Street, Longwood Drive, Edgewood Drive, Wilding Chase, Walnut Street and River Run Park parking lot

OVERVIEW

The annual Road Program is a yearly program that encompasses multiple projects with the aim to improve roadways throughout the Village.

TIME-FRAME

Start Date: October 18, 2021
Projected Completion Date: November 12, 2021

BUDGET

$547,083.00 [ Burton Scot Contractors ]

STATUS UPDATES

DATEDESCRIPTIONRESOURCE(S)
10/06/2021Press Release: 2021 Road Program StartingDocument
09/00/2021Bid Awarded to Burton Scot