East Washington Street Improvement Project – Schedule Change Notification (8/19/20)

PRESS RELEASE NOTICE:

The East Washington Street Improvement Project is well underway and utility work in the section of the street between Cleveland Street and Ridgewood Road is nearing completion.  Due to changing project variables, there will be a change in the schedule for the project moving forward.  The updated schedule is as follows:

  • Philomethian Street to Cleveland Street – Monday, August 24 through Friday, October 2
  • North Main Street to Philomethian Street – Monday, September 28 through Friday, November 6
  • Ridgewood Road to Billy Campbell Boulevard – Monday, November 2 through Friday, November 27
  • PAVING WORK THROUGH THE ENTIRE PROJECT AREA – Wednesday, November 4 through Friday, November 20, weather-permitting
Utility WorkAugSeptOctNov
Philomethian to ClevelandM 8/24 F 10/2 
North Main to Philomethian M 9/28F 11/27
Ridgewood to Billy Campbell Blvd   M 11/2 – F 11/27
PavingAugSeptOctNov
Entire project area *weather permitting   W 11/4 – F 11/20

Major work resulting in full road closures will be performed in the first two sections listed above.  Accommodations will be made to allow access for property owners in each closed block traveling in the EASTBOUND direction only.  Work in the section east of Ridgewood Road as well as the paving work throughout the entire project area will not require a full road closure, as traffic will be managed with flaggers for both of these phases of the project.  

Traffic will be detoured to BELL STREET for the full road closure periods.  Signage has been posted for the detour route.  This schedule is approximate and subject to change due to weather and project variables.  Village staff, our engineer, and the contractors on the project will work to minimize disruption and inconvenience during this major project.

Letters to each property owner reporting the condition of your sanitary sewer lateral and the cost to have it relined, if needed, as part of this project will be mailed out within the next one to two weeks.

This project is scheduled to reach completion around December 1, 2020.  Further information will be posted when announced throughout the duration of the project.  This project is funded by low-interest loans from the Ohio EPA and a grant from the Ohio Public Works Commission.  Thank you for your patience and cooperation as we look to complete this project in an efficient manner.

Respectfully,

Robert S. Jamieson
Chief Administrative Officer

Printable Press Release

Enter High School Campus via Ridgewood (traffic pattern change notification)

Due to the progression of the E. Washington Street project, the Village has a slight change in the construction traffic pattern previously noted that impacts entrance to the High School campus.  Work within the construction zone will now necessitate a change to the original traffic plan. 

As school practices have resumed; coaches, parents and athletes please be advised of these changes impacting how to access the High School campus safely. 

Starting now, all motorists should enter the High School campus via Ridgewood > E. Washington > High School. 

Motorists ARE NOT PERMITTED to drive around the barricades at Cleveland Street eastbound continuing on E. Washington to access the High School campus, they must follow the detour.   

Public Meeting – ABR – 289 North Street (8/18, 8:30 AM)

NOTICE OF PUBLIC MEETING

Office of Building & Zoning Department

August 7, 2020

Notice is hereby given pursuant to Sections 1109.05(B)(1)(b) & 1125.04 (A) (6) Review and Approval procedures of the Codified Ordinances of Chagrin Falls that a meeting will be held by the Architectural Board of Review, of the Village of Chagrin Falls, Tuesday, August 18, 2020 at 8:30 AM in a virtual meeting utilizing the Zoom platform. 

To hear a proposal: Accessory Structure greater than 18 feet in height.

Project Address: 289 North Street, Chagrin Falls, Ohio 44022

Permanent Parcel No. 931-06-004

In accordance with Sub. HB 197, this meeting will be held as a remote meeting, no one will be in attendance at the Village Council Chambers, and the public is not permitted to access the Council Chambers during the meeting. Access is available to the public only via telephone, YouTube and through Zoom web conferencing. Instructions on joining the meeting using these methods is listed on the village website at www.chagrin-falls.org.  If you wish to view the project plans prior to the meeting, please contact Harry Edwards, Building and Zoning Inspector, at (440) 247-5050 or at harry@chagrin-falls.org

If you wish to comment on this proposed project, you are encouraged to do so at the hearing and prior to the Architectural Board of Review’s action on the requested proposal. Please be advised there are limited circumstances for modification to a proposal once acted upon by the board. The appropriate time to comment on the proposal is at the time of the scheduled meeting referenced above.

______________________________

Harry Edwards
Building and Zoning Inspector